BDHG adopts multisource networking heating, the total length of the heating pipeline is 1429 km, and the heating area is 254 million square meters, the heating station adopts the indirect heating and transferring mode, the total number is about 3507.
The system adopts the concept of integrated data platform and supports multi-center sharing architecture, includes: the group dispatch center, sales dispatch center, branch office dispatch center, group organization and other data center and application level. The control host machine adopts xLink3000 controller based on China Telecom CDMA\3G communication network platform, the project has completed more than 2,521 monitoring stations, of which there are about 1,480 thermal stations, about 200 unattended stations, and about 42 stations of the power plant outlet heat source measurement. After many years of expansion, the system has become the heating monitoring system which has the widest coverage and the most control stations in the national heat industry.
![北京热力集团供热监控系统 北京热力集团供热监控系统]()